District Cooling in the air in Jordan
The Abdali area in Jordan’s capital, Amman, needed cooling and heating solutions customised to suit the ambience of the upmarket hub, while working within the constraints of the country’s climatic conditions and water scarcity. Araner proposed a design based on air-cooled chillers with zero water consumption. We bring you the case study…
THE BACKGROUND
Abdali is Amman’s new downtown district that provides the Jordanian capital with the central business, social and residential destination it needs as a regional business and tourism hub.
An ample investment for the creation of modern and luxury buildings, towers, residences, business centres and commercial areas has been developed with a total value of more than USD 5 billion. A lot of green areas, parks and a central boulevard have also been included in the project for people to get around on foot and enjoy the scenery. Araner, an engineering group specialising in refrigeration, cooling and heating, was tasked with finding thermal comfort solutions.
CASE-IN POINT
The challenge – what did Abdali need? The weather in Amman is quite extreme – incredibly high temperatures during summer and freezing night-time temperatures in winter make it difficult to live indoors without heating and air conditioning. Amman has another handicap, which introduced further challenges to the project: Water availability is scarce. Typically, a 52,000 TR cooling plant water consumption is out of the range that Amman can afford to supply.
THE SOLUTION:
District Cooling was selected as the most efficient and reliable solution for the chilled and hot water supply of the new development. The total cooling capacity was calculated to be 52,000 TR. Efficiency is a crucial parameter for these kinds of plants, as the amounts of energy consumed throughout the year is very high. Any improvement in efficiency would result in huge savings in any developer’s running costs. Reliability was also a must, as so many residences, hotels, people and businesses depend on it. Those requirements are typical of any District Cooling plant worldwide.
The original solution considered in the early design stages was a District Cooling plant with centrifugal chillers and cooling towers. Cooling towers constitute the traditional solution implemented in District Cooling plants in order to increase the chiller’s efficiency. However, the disadvantage of cooling towers is that they have a very high water consumption rate. The original design concept would have implemented a grey water supply from the municipality that would be treated in a water treatment plant inside the District Cooling Plant. The problems with this solution were threefold:
The main challenge of the project execution was to achieve these two deadlines within a tight framework, bearing in mind that within 274 calendar days (nine months), only the skeleton of the building and half of the tank, where the electrical rooms should be placed, would be erected.
In order to reach these targets, close coordination between civil, mechanical, electrical and control departments was undertaken to install all of the equipment with the required quality and within a very tight schedule.
Araner’s personnel from different departments were mobilised to the site to supervise the installation and commissioning of the main equipment.
For Milestone 2, the chillers installed in the temporary plant were dismantled and delivered to Araner’s workshop in Spain, in order to carry out maintenance and install all the improvements that had been developed by Araner’s engineering team during the past years.
Changes to the discharge line, modifications in the oil separator supports, rearrangement of the interior piping or oil separator filters were just some of the modifications that were applied in the compressor units in order to improve their performance.
Thanks to the quality of equipment installed in the compressor units and good maintenance performed by the company’s O&M team, the components were still in perfect condition after six years of working.
Once all the equipment was installed at site, and due to pre-installation being carried out to a high degree of precision, it took just 30 days from the plant being energised by the local electricity authority (JEPCO) before starting the supply of chilled water to the network.
The following tests were performed with a professional and multidisciplinary team from Araner:
CPI Industry accepts no liability for the views or opinions expressed in this column, or for the consequences of any actions taken on the basis of the information provided here.

- The capital cost of the water treatment plant
- The operation and maintenance of the plant, mainly due to the extensive chemical treatment required and the cost of the waste management
- Water treatment plants usually emit undesirable odours, which are not compatible with the level of luxury desired for the new developments.


- 33/11 Oil Transformers Energising and Commissioning
- MV Panels Energising and Commissioning
- 11/0.4 kV Dry-type Transformers Energising and Commissioning
- LV Panels Energising and Hot Commissioning
- Heat Rejection Devices Commissioning
- Production Pumps Commissioning
- Consumption Pumps Commissioning
- Chilled water System Flushing
- MV Motors Commissioning
- Compressor Units Commissioning
- Safety and Emergency Systems Commissioning
- FF & FA Commissioning
- Control System Tests